Approve Change Order #1F for Corr Construction Services Inc for 2015 Bridge Maintenance Project, Project No. 15-2262 / CIP No. 50752, for an increase of $11,593.75.

 

 

Summary:

Increase to the contract based on actual quantities installed.   